Terminal T3 – Tan Son Nhat Airport Takes Shape After Nearly 2 Years of Construction

2024-09-01 16:48:56

(KTSG Online) – After nearly 2 years of implementation, Terminal T3 – Tan Son Nhat Airport has reached about 70% of the total construction volume of the project. Currently, the contractor consortium has mobilized over 2,500 engineers and workers to ensure the project is operational by April 30, 2025. 

Source of article from Saigon Online Economy: see original article here.

01-Nhà ga T3 – sân bay Tân Sơn Nhất thành hình sau gần 2 năm thi công

Terminal T3 – Tan Son Nhat Airport broke ground in December 2022. However, due to obstacles in land clearance, the main contract package for “Construction and Installation of Equipment for the T3 Passenger Terminal” didn’t commence until the end of August 2023. After nearly a year of construction for the main contract, the project has now completed 100% of the structural frame of the passenger terminal and is rapidly working on items such as installing steel components above to cover the terminal’s roof and connecting the electromechanical systems.

02-công tác lắp dựng kết cấu thép, vách kính và lợp mái nhà ga

Mr. Le Khac Hong, Head of the Project Management Board for Terminal T3, stated that the installation of steel structures, glass walls, and roofing for the terminal is conducted in a staggered manner. The first group of workers installs the steel structure, while the second group proceeds with roof installation and glass wall assembly in tandem. Currently, the contractor has mobilized more than 100 workers to install the first layer of the roof, achieving about 60% of the total roof area.

03-Hệ thống kết cấu thép vòm không gian chịu lực khung mái che đã lắp đặt hoàn thiện.

The spatial truss structure of the roof has been fully installed.

04-lắp đặt các cấu kiện thép nhà thầu phải sử dụng nhiều loại cần cẩu từ 100-600 tấn thi công.

The representative of the T3 terminal project management board stated that to install the steel components, the contractor must use various types of cranes ranging from 100 to 600 tons for construction.

05-Dự kiến hạng mục lắp dựng mái cho nhà ga T3 sẽ hoàn thành tháng 2-2025.
default

The roof installation for T3 terminal is expected to be completed by February 2025.

06-công nhân hối hả thi công hệ thống điện, khí, cấp thoát nước

Inside the terminal, workers are busy working on the electrical, air, water supply, and drainage systems. The pipe systems, technical boxes, and central control station have basically taken shape.

07-công nhân tại công trường đang thực hiện cắt sắt để thi công hệ thống treo cho hạng mục cơ điện

The photo shows a worker at the construction site cutting steel to build the hanging system for the electromechanical section inside the terminal.

08-các hạng mục cơ điện và lắp đặt thiết bị vận hành sẽ lần lượt hoàn thành vào tháng 3 và tháng 4-2025.

According to the investor’s calculations, it is anticipated that the electromechanical items and equipment installation will be completed in March and April 2025, respectively.

09-Hệ thống cầu cạn trước nhà ga đã hoàn thành hạng mục bê tông cốt thép.

The elevated bridge in front of the terminal has finished its reinforced concrete segment. Once completed, this bridge will connect to the Trần Quốc Hoàn – Cộng Hoà junction.

10-Cầu cạn này có nhiệm vụ chia tách dòng xe lên các tầng của nhà ga T3.

This elevated bridge is responsible for channeling vehicle traffic to the various levels of the T3 terminal.

11-Nhà ga T3- sân bay Tân Sơn Nhất view từ trên cao

The T3 terminal at Tan Son Nhat Airport has one basement level and four above-ground levels, built over an area of 112,500 m². The project has a total investment of more than 10.9 trillion VND. Once completed, it will be a domestic passenger terminal with a capacity of over 20 million passengers per year, capable of accommodating all types of large aircraft. The T3 terminal will be connected to the airport by internal airport roads through a shuttle bus service. Traffic connectivity to the terminal will be facilitated by separate entry and exit bridges.